BREAKING: Umahi disapproves Julius Berger’s N279bn cost for Second Niger Bridge bypass

Reportgist
2 Min Read
- Advertisement -

The Minister of Works, Senator David Umahi, has rejected and described as excessive Julius Berger Plc’s proposed cost of N279 billion for the Second Niger Bridge Bypass. Umahi, in a statement issued on Thursday, expressed his disappointment with Julius Berger’s pricing of the project.....CONTINUE READING THE ARTICLE FROM THE SOURCE

“One of the bypasses, which is 17.27 kilometres by two on asphalt, was awarded to Julius Berger. We changed the pavement elements to concrete, and the cost we calculated was N133 billion. Berger presented a figure almost twice our estimate, at N279 billion,” he said.

READ:  Some People Almost Killed Me At Mushin When They Accused Me Of Being A Witch -Iya Gbonkan

“We disagreed with this cost during the negotiation in September 2023. We’ve decided to refer the project back to the Bureau of Public Procurement (BPP) and invite more contractors to bid because this involves public funds.”

The Federal Ministry of Works has reviewed Julius Berger Plc’s performance on all ongoing projects awarded to the company, with Umahi raising concerns over the unacceptable condition of some projects, including the Lagos-Ibadan Expressway phase 2.

- Advertisement -

The former Ebonyi State Governor explained that his ministry would seek selective tendering to complete the project.

READ:  Food Crisis: FG: We've Finally Found the Solution to the Food Shortage

“We changed the pavement elements from asphalt to concrete, and the total cost we calculated based on prevailing rates is N153 billion,” Umahi noted.

- Advertisement -

“However, they are proposing N258 billion. Since we’ve been negotiating since September 2023, we have no choice but to terminate this contract.

“We will then request a ‘No Objection’ from BPP for selective tendering, submitting our estimate of N153 billion and their proposal of N258 billion to BPP, while inviting other contractors to bid. This process will be concluded within the next month to ensure the project is completed promptly.”